Pool Excavation Allowances and When to Issue a Change Order

Set a haul allowance the crew can track, document work outside the bid, and get written approval for the price and schedule change before proceeding.

Editorial desk   ·   2026-11-29
Two excavators on construction site with dirt piles
Photo by Annie Spratt on Unsplash

A pool excavation allowance is a quantity of work included in the bid, such as a set number of spoil-hauling trips at an agreed truck capacity. Issue a written change order when hauling will exceed that quantity or when a buried obstruction or layout revision changes the agreed scope. Show the client the price and schedule impact and get written approval before proceeding with the changed work.

Put a quantity beside the allowance

Attach a dated layout to the bid showing the dig limits, equipment access and spoil staging area. If the base price includes hauling, specify the number of trips, the assumed capacity per truck in loose cubic yards, and how partial loads count. Use haul tickets to track trips against the allowance. State whether unused trips earn a credit and what the rate for an extra trip covers. If site access calls for a different truck, agree before digging on how to recalculate the allowance and extra-trip rate.

Agree on when the crew will pause

Name the person who can approve a change order on the allowance sheet. If the crew needs another haul trip, finds a buried obstruction that changes the dig, or needs to move or resize the pool on the dated layout, pause the affected work and secure the area. Send the approval contact photos and a quantity estimate or a marked-up layout, as applicable. Put the proposed work, price and schedule adjustment in the change order. Resume the affected work after written approval and any applicable safety and permit checks.

Assign pre-dig responsibilities in Mississippi

Mississippi 811 says the person or company performing the excavation must submit the locate request. Mississippi 811 guidance on who submits the locate request

Mississippi 811 says utility companies generally mark from the street to the meter, or to the property line if there is no meter. Mississippi 811 guidance on utility marking limits

Mississippi 811 places responsibility for locating privately owned lines on the property owner. Mississippi 811 guidance on locating privately owned lines

Before mobilization, confirm that the property owner has made separate arrangements to locate any privately owned lines in the work area.

If the project involves a Mississippi onsite wastewater application, the Mississippi State Department of Health asks for a plot plan showing current and planned property features, including pools. Mississippi State Department of Health guidance on onsite wastewater plot plans

When that plot plan applies, compare it with the bid layout before proposing a shift in the pool footprint.

Worked example with a fifth haul load

In this hypothetical bid, the price includes four truck trips, each with an agreed capacity of 10 loose cubic yards. A partial load counts as one trip. After checking the four haul tickets, the foreman measures the remaining spoil pile. It covers roughly 12 by 9 feet and averages about 2 feet deep. That gives an estimated 216 cubic feet, or 8 loose cubic yards, which fits in one more truck at the agreed capacity.

The agreed extra-trip rate is $450, including loading, hauling and disposal fees. One additional trip adds $450 to the contract. In this example, the next truck is available the following morning, so the change order moves the next scheduled excavation task back half a workday, assuming approval by the end of the current workday. The foreman sends the four haul tickets, a photo of the pile, the volume estimate and the priced change order. The foreman waits for written approval before dispatching the truck.

Before sending your next bid, attach the dated layout and put the client’s approval contact on the allowance sheet. For related bid-pricing guidance, see How to Price Bid Alternates for Pool Deck Restoration.